The plan applies to Coal-fired electric steam generating units and coal-fired electric generating units as defined in 40 CFR 60.24(h)(8) including the following existing coal-fired electric generating units:
(a)Big Cajun 2 (Unit 1) at New Roads, LA.
(b)Big Cajun 2 (Unit 2) at New Roads, LA.
(c)Big Cajun 2 (Unit 3) at New Roads, LA.
(d)Rodemacher (Unit 2) at Lena, LA.
(e)R.S. Nelson (Unit 6) at Westlake, LA.
(f)Dolet Hills at Mansfield, LA. [72 FR 46164, Aug. 17, 2007]